About Zanpa Beach beach maintenance work (March 3-March 31)
2025/02/28
The beach maintenance work will be carried out on the following schedule with the opening of Zanpa Beach in 2025.
During the construction period, access to Zanpa Beach will be restricted.
The beach can be used during the construction period, but it will cause inconvenience and inconvenience to beach customers such as generating construction sounds and traffic of construction vehicles.
Records
Construction period March 3 to March 31
Construction area Zanpa Beach beach area
Construction schedule
Early to mid-March estimated sand drilling, accumulation and transportation work
Mid-March to late March sand transport, leveling and leveling work
Installation of jellyfish prevention nets and marine athletics
※During the construction period, Malin activities and rental items are available.
※The construction schedule is subject to change depending on the weather and other progress.
※The sea opening (swimming starts) is scheduled from April 1st.
It will be an important work to prepare for the opening of Zanpa Beach on April 1 and to prepare a safe and secure beach environment for everyone who uses it, so we appreciate your understanding and cooperation.