About the beach construction associated with the opening of Zanpa Beach and the opening of the sea (February 1-February 28)
2026/01/21
In April 2026, we will carry out the beach maintenance work on the following schedule with the opening of Zanpa Beach.
During the construction period, access to Zanpa Beach may be partially restricted.
You can use the beach during the construction period, but we are very inconvenienced and inconvenienced to beach customers such as generating construction sounds and traffic of construction vehicles.
※During the construction period, Malin activities and rental items can be used.
※The construction schedule is subject to change depending on the weather and other progress.
※The sea opening (swimming starts) is scheduled from April 1, 2026.
[Construction period] From February 1, 2026 to February 28, 2026
[Construction area] Zanpa Beach Seaside Area
[Construction Schedule]
- Early to mid-February estimated sand drilling, accumulation and transportation work
- Mid-February to late February sand transport, leveling and leveling work
[Other schedule] End of March 31, net for preventing jellyfish and sea athletic installation, etc.
April 1 It will be an important work to prepare for the opening of Zanpa Beach Sea and to prepare a safe and secure beach environment for everyone who uses it. Thank you for your understanding and cooperation.